Fit-Out Timeline Calculator: How Long Will Your Office Take?

A fit-out timeline estimate adds design, approvals, site works, procurement, installation and handover into one programme. Site works and long-lead procurement run in parallel, so whichever takes longer sets the handover date. That phase is the critical path.

By Dhruv Agarwal · · 4 min read

Fit-out timeline estimator

sq ft
weeks

Use 0 if approved working drawings already exist.

weeks
weeks

Order to delivery for the slowest item, e.g. imported furniture or HVAC units.

Assumptions (edit to match your project)
sq ft a week

Area completed through civil, MEP, ceiling and finishes each week.

weeks
weeks
weeks

Indicative programme

18 weeks

About 4.2 months

Site works

7.7 weeks

Mobilisation to finishes

Critical path runs through

Procurement

The 8-week lead item, not the site, sets the date

From approval to handover

11 weeks

Programme

Design and drawingswk 0–4
Landlord and authority approvalswk 4–7
Site works: civil, MEP, ceiling, finisheswk 7–14.7
Long-lead procurementwk 7–15
Furniture installation, testing and commissioningwk 15–17
Snagging and handoverwk 17–18

Darker bars are on the critical path.

How this was calculated

  • Site works = 1 + (10,000 / 1,500) × 1 × 1 = 7.7 weeks
  • Parallel stage = max(site works 7.7, lead item 8) = 8 weeks
  • Total = 4 + 3 + 8 + 2 + 1 = 18 weeks

Send this result on WhatsApp

Your figures go with the message, so our team can reply on them directly.

Send on WhatsApp

Get a detailed quote

Indicative figures for early planning, based only on the inputs and assumptions above. This is not a design, a quotation or a compliance check. A qualified engineer or consultant must confirm any figure before it is used to order, build or sign.

What it calculates

The estimator builds an indicative fit-out programme in weeks, from the start of design to handover. It shows:

  • the total programme in weeks and months;
  • the site works duration, from mobilisation to finishes;
  • which phase sits on the critical path, site works or procurement;
  • the time from approval to handover;
  • a simple bar chart of the phases, with the critical ones highlighted.

Inputs

Carpet area is the area being fitted out.

Starting condition describes what is already there. A bare shell has no ceiling, air conditioning or lighting. A warm shell has them in place, so less work is needed. An existing office has to be stripped out before new work starts.

Working hours allowed by the building reflects the landlord's rules. In occupied buildings, noisy work is often limited to nights and weekends.

Design and drawings is the time to produce approved working drawings. Enter zero if they already exist.

Landlord and authority approvals is the wait between submitting drawings and receiving permission to start.

Longest lead item is the time from order to delivery for the slowest item on the project, often imported furniture, specialist glass or HVAC equipment.

The assumptions panel holds the weekly site progress, mobilisation, installation and commissioning, and the handover period.

Method

The programme runs in five stages. The third stage has two activities in parallel:

  1. Design and drawings.
  2. Approvals.
  3. Site works and long-lead procurement, both starting when approval is received. Site works = mobilisation + (area ÷ weekly progress) × condition factor × hours factor.
  4. Furniture installation, testing and commissioning, which starts when both the site works and the long-lead delivery are complete.
  5. Snagging and handover.

Total = design + approvals + the longer of site works and procurement + installation + handover.

Assumptions

AssumptionDefaultNotes
Site progress1,500 sq ft a weekArea taken through civil, MEP, ceiling and finishes each week
Mobilisation1 weekSite set-up, protection, permits to work
Bare shell factor1.0The reference case
Warm shell factor0.75Less ceiling and services work
Existing office factor0.9Strip-out first, but some services may be reused
Night and weekend factor1.4Shorter, less productive shifts
Installation, testing and commissioning2 weeksFurniture, then testing of services
Snagging and handover1 weekDefects list, cleaning, documents

Weekly progress depends heavily on the specification and the size of the team on site. A simple open-plan office progresses faster than a floor of cabins, glass partitions and detailed joinery. Change the figure to suit the project.

Limitations

  • It assumes approvals arrive in one go. In practice, landlords often comment and ask for resubmission, and each round adds time.
  • It treats site works as one block. A real programme overlaps trades and tracks dozens of activities, some of which depend on deliveries other than the longest one.
  • It assumes the order is placed on approval. If decisions on furniture or finishes are late, procurement starts late and the programme moves with it.
  • It does not allow for client changes. Changes after work has started are one of the most common causes of delay.
  • It ignores external events. Authority inspections, power connections and building works by the landlord can all hold up handover.

Worked example

A 10,000 sq ft bare-shell office, normal working hours, four weeks of design, three weeks of approvals and an eight-week lead time on imported furniture:

PhaseCalculationWeeks
Design and drawingsentered4
Approvalsentered3
Site works1 + (10,000 / 1,500) × 1.0 × 1.07.7
Long-lead procuremententered8
Parallel stagethe longer of 7.7 and 88
Installation and commissioningassumed2
Snagging and handoverassumed1
Total4 + 3 + 8 + 2 + 118

The programme is about 18 weeks, a little over four months. Procurement, not the site, sets the date: the furniture arrives a few days after site works finish. Placing the order two weeks earlier, for example by approving the furniture during design, would bring handover forward by the few days procurement is ahead of the site.

If the same floor can only be worked at nights and weekends, site works stretch to about 10.3 weeks and become the critical path. The programme grows to about 20.3 weeks, and ordering early no longer helps.

How engineers use it

A project manager builds the programme in the same way: fix the dates that cannot move, identify the long-lead items, and find the chain of activities that sets handover. The difference is detail. A real programme breaks site works into trades and areas, links them with dependencies, and tracks deliveries item by item.

The most useful output at the early stage is knowing what is on the critical path. If it is procurement, the decisions that matter are about ordering early. If it is site works, they are about working hours, labour on site and avoiding changes.

When a professional design must replace it

Use the estimator to set expectations, to test what a later lease start or a night-only rule does to the date, and to decide which decisions must be made early. Replace it with a contractor's detailed programme before you commit to a move-in date, a lease start or a notice period on your current premises, and keep that programme updated as the project runs.

Frequently asked

It depends far more on approvals, lead times and working hours than on area alone. A mid-sized office with design still to do can easily take four months or more from appointment to handover, while a small warm-shell refresh with drawings ready can be much quicker. Enter your own figures to see which phase dominates.

It is the chain of activities that sets the finish date. Delay anything on it and handover moves; delay something off it and handover does not, up to a point. In many fit-outs the critical path runs through a long-lead item such as imported furniture or HVAC equipment rather than through site work.

Many occupied buildings allow noisy or dusty work only at night or at weekends. Shorter shifts, mobilising and clearing up each night, and restrictions on deliveries all reduce how much gets done each week. The calculator applies a factor to site works to reflect that; change it if your building's rules are different.

Only if procurement is on the critical path. If the longest lead item takes more weeks than the site works, placing that order the day the design is approved, or before, brings handover forward. If site works are longer, ordering earlier changes nothing.

No. The programme starts when the design work starts. Lease negotiation, landlord consents before signing and any rent-free period discussions come before it.