Office Relocation Timeline: Lease Signing to Move-In

An office relocation timeline runs from lease signing to the first working day, not from the first day on site. The time goes into building due diligence, landlord approvals, design and design freeze, long-lead ordering, the fit-out, IT and AV commissioning, and the move itself. Several stages run in parallel; the date is set by the longest chain, which depends on size and building.

By Dhruv Agarwal · · 7 min read

The move date is decided before anyone is on site

Most relocation plans begin with one question: how long will the fit-out take? It is the natural question, because the site work is the visible part. It is also the wrong place to start.

The site work is the middle of an office relocation timeline, not the whole of it. Before it sit the lease terms, the building's rules, the brief, the design and the ordering of items that take weeks to make. After it sit the IT cut-over, commissioning, snagging and the move itself. The date a company can move in is usually decided in the first few weeks after the lease is signed, by how quickly those early decisions are made, not by how fast a contractor builds.

For a CEO or CFO this matters for a simple reason. The cost of a late move is rarely the fit-out. It is two rents running at once, a notice period that has already expired on the old premises, or a team without a workplace.

Where the weeks actually go

Each stage below has its own owner and its own reasons to slip. The durations are not given here because they genuinely depend on the size of the space and the building; what matters is the sequence and what each stage waits for.

StageWhat happensWhat it typically waits for
Building due diligenceSite survey, base-building drawings, power and cooling capacity, landlord fit-out guidelinesAccess to the space and documents from the landlord
Lease termsFit-out period, handover condition, works approval process, exit obligationsNegotiation before signature
Brief and designHeadcount, layout, design development, services design, design freezeClient decisions on space, budget and standards
ApprovalsLandlord design approval; any statutory approvals the consultants identifyA complete, coordinated design submission
Long-lead procurementPartitions, joinery, air conditioning equipment, specified lighting, raised floor, furnitureDesign freeze and approved samples
Fit-out on siteDemolition, services, ceilings, partitions, finishesApprovals, materials on site, permitted working hours
IT, AV and securityInternet circuits, network cabling, wireless, AV, access controlContainment installed; service provider lead times
Commissioning and handoverTesting services, snagging, documentationCompleted installations and a working power supply
The movePacking, furniture placement, IT cut-over, staff inductionA handed-over space with working systems
Exit from old premisesReinstatement, handback, deposit settlementThe move being complete

None of these stages is unusual. What makes a relocation late is treating them as a single line that starts when the contractor arrives.

The early weeks: due diligence and the lease

The weeks just before and after signing do more to fix the move date than any later stage.

Due diligence on the building. A survey of the actual space, the base-building drawings, the landlord's power and cooling provision and the fit-out guidelines tell you what the design has to work within. The rules a building imposes on ceilings, shafts, working hours and approved vendors are covered in reading the landlord's fit-out guidelines before design. Discovering them after the layout is drawn is one of the commonest causes of a redesign.

The lease terms. The fit-out or rent-free period, the condition the space is handed over in, how the landlord approves tenant works, and what must be reinstated at exit all shape the programme. A space handed over with ceilings, lighting and air conditioning already in place is a different starting point from a bare floor, and it changes how much of the programme sits with the tenant.

What runs in parallel, and what cannot

A relocation is fast when the right things overlap and the wrong things do not.

What can run in parallel:

  • Ordering internet circuits and connectivity while the design is still being developed, because service provider lead times are outside anyone's control.
  • Furniture selection and sampling alongside design development.
  • Landlord review of the design while non-dependent packages are priced.
  • Planning the exit from the old premises, including its reinstatement obligations, while the new one is being built.

What must stay in sequence:

  • Design freeze before long-lead items are released. Ordering against an unsettled design is how variations begin.
  • Services above the ceiling installed and tested before the ceiling closes.
  • Network cabling and containment installed before ceilings and partitions close around them.
  • Commissioning before the move, not after it. Moving staff into a space whose air conditioning and fire systems have not been tested shifts the problem onto the first working week.

The logic of the site sequence itself, including design freeze and long-lead items, is set out in fit-out programme and phasing.

What a CEO or CFO must decide early

Most delays in a relocation trace back to a decision the business had not yet made. These are the ones that hold everything else:

  • Headcount and growth assumption. The number of people the space is planned for, and for how long. Changing it after freeze changes the layout, the services and the furniture order.
  • Budget envelope and approval route. Who approves spend, at what level, and how quickly. A design waiting for budget sign-off is a programme on hold.
  • Contract structure. Whether design and construction sit with one party or are tendered separately, which changes how much of the design and construction can overlap.
  • The overlap with the old premises. How long both leases run together. A short overlap saves rent and removes the safety margin; a long one does the reverse.
  • Reuse or replace. Whether existing furniture, IT equipment and AV move across. Reuse saves procurement time only if the items are surveyed early.
  • Design authority. One named person who can approve the design and changes to it, with a date by which they will do so.

A wider view of how these decisions fit into the whole project is in the office fit-out guide for India.

The exit is part of the same timeline

Relocations are usually planned as an arrival. They are also a departure, and the old lease carries its own obligations: a notice period, a handback date, and often a duty to reinstate the space to a stated condition. Reinstatement takes time on site and has to be finished before the handback date, which means it starts only once the move is complete.

If the two timelines are planned separately, the overlap is often too short to fit both the move and the reinstatement. What the landlord can typically ask for at exit, and how to limit it, is covered in lease-end reinstatement: what you owe the landlord.

Common mistakes

  • Starting the clock at mobilisation. The programme is agreed for the site work only, and the weeks of design, approvals and ordering are not in it.
  • Signing the lease before reading the guidelines. The fit-out period is agreed without knowing the building's working hours or approval process.
  • Ordering connectivity late. Internet circuits are requested near the end, and the space is ready before the network is.
  • Letting the brief move after freeze. A change in headcount or departments arrives once long-lead items are already ordered.
  • Treating commissioning as optional time. It is squeezed to protect the move date, and the faults appear in the first month of occupation.
  • No overlap with the old premises. A small delay becomes a period without an office.
  • Forgetting the exit. Reinstatement of the old space is not planned, and the handback date arrives before it is finished.

What to ask before signing the lease

  • What condition will the space be handed over in, and on what date?
  • Have we read the full fit-out guidelines and the base-building drawings?
  • How does the landlord approve tenant designs, and how long does that review take?
  • Is the fit-out or rent-free period long enough for design, approvals, ordering and site work, not just site work?
  • What is the notice period on the current premises, and what must be reinstated there?
  • Who on our side owns the programme and can approve the design?
  • Which items in our likely design are long-lead, and when must they be ordered?

A design-and-build contractor should be able to turn these answers into a programme that starts at lease signing, and show which chain of activities sets the date.

Standards referenced

Fire and life safety provisions in NBC 2016, Part 4, and building services provisions in NBC 2016, Part 8, both relevant where the fit-out alters detection, sprinklers, air conditioning or electrical services; commercial building telecommunications cabling in TIA-568. Whether any statutory approval applies to a particular fit-out, and how long it takes, is determined by the project's consultants and the authority having jurisdiction. Lease terms, notice periods and exit obligations are set by each lease and should be confirmed with the client's legal adviser.

Standards referenced

  • NBC 2016, Part 4 — Fire and life safety (Bureau of Indian Standards)
  • NBC 2016, Part 8 — Building services (Bureau of Indian Standards)
  • TIA-568 — Commercial building telecommunications cabling (Telecommunications Industry Association)

Frequently asked

It depends on the size of the space, the condition the landlord hands it over in, the building's rules and how quickly decisions are made. A small floor in a well-documented building can move much faster than a multi-floor fit-out with heavy services. Any duration quoted before the building has been surveyed and the brief settled is a guess, not a programme.

Before the lease is signed. The lease fixes the fit-out period, the handover condition and the rules for tenant works, and the notice on the current premises fixes the latest date you can leave. Both decide the timeline, so they are best negotiated with the programme in view rather than discovered after signature.

Late decisions more often than slow site work. A brief that keeps changing, a design freeze that slips, landlord approval that was not planned for, long-lead items ordered late, and internet circuits requested too close to the move are the common causes. Each of these happens before or alongside the site work, which is why they are easy to underestimate.

Some early packages can, such as demolition of existing fit-out, enabling works or base services modifications that do not depend on the final layout. Anything that depends on the layout, the ceiling or the services design should wait for freeze. Starting those early usually creates rework that costs more time than it saved.

Usually some overlap is wise, because a move date that slips with no office to fall back on is a business continuity problem, not a fit-out problem. The overlap costs rent on two premises, so its length is a commercial decision to take early, with the exit and reinstatement obligations on the old premises in view.

One named person on the client side, with authority to make decisions, working with the design-and-build contractor or project manager. The fit-out contractor can run the construction programme, but decisions on headcount, IT, furniture, notice periods and staff communication belong to the business and need an owner.