Fit-Out Quotation Comparison: Put Three Quotes on One Basis

A quotation comparison puts several contractors' prices on the same basis before they are compared: the same treatment of GST, the cost of anything one quote leaves out added back, and the cash each asks for up front or holds back shown side by side. Without that, the lowest headline number is often not the lowest cost.

By Dhruv Agarwal · · 4 min read

Fit-out quotation comparison

sq ft

Optional. Gives a cost for each sq ft of carpet.

Enter from each quoteQuote AQuote BQuote C
Quoted amount₹
GST in the quoted amount?
Your estimate of items left out₹, before GST
Provisional sums inside the quote₹
Advance asked%
Retention held%
Programmeweeks
Defects liability periodmonths
Assumptions (edit to match your project)
%

Confirm the rate for your contract with your accountant.

Enter the quoted amount for at least two quotes to compare them.

How this was calculated

  • Quoted before GST = amount, or amount / (1 + GST rate) when GST is included
  • Comparable = quoted before GST + your estimate of items left out
  • Advance and retention are worked out on the quoted amount with GST
  • Provisional share = provisional sums / quoted before GST

Send this result on WhatsApp

Your figures go with the message, so our team can reply on them directly.

Send on WhatsApp

Get a detailed quote

Indicative figures for early planning, based only on the inputs and assumptions above. This is not a design, a quotation or a compliance check. A qualified engineer or consultant must confirm any figure before it is used to order, build or sign.

What it calculates

The comparison takes up to three fit-out quotations and shows, side by side:

  • each quote before GST, whether it was quoted with GST or without;
  • a comparable price that adds back your estimate of what each quote leaves out;
  • the comparable price with GST;
  • how far each quote is above the lowest, in rupees and as a percentage;
  • the cost for each sq ft of carpet area, if you enter the area;
  • the share of the price that is provisional and could change;
  • the cash paid as advance and the cash held as retention.

All figures are yours. The calculator stores nothing and starts blank.

Inputs

For each quote:

  • Quoted amount: the total on the quotation.
  • GST in the quoted amount?: whether the total includes GST or GST is added on top.
  • Your estimate of items left out: the cost, before GST, of anything you need that the quote excludes.
  • Provisional sums inside the quote: the total of allowances that will be re-measured.
  • Advance asked: the percentage paid before work starts.
  • Retention held: the percentage kept back until the defects period ends.
  • Programme and defects liability period: for reference alongside the price.

Optionally, the carpet area the quotes are for, and in the assumptions panel the GST rate.

Method

  1. Quoted before GST = the quoted amount, or the amount divided by (1 + GST rate) when the amount includes GST.
  2. Comparable before GST = quoted before GST + your estimate of items left out.
  3. Comparable with GST = comparable before GST × (1 + GST rate).
  4. Above the lowest = comparable before GST − the lowest comparable before GST.
  5. Cost for each sq ft of carpet = comparable before GST ÷ carpet area.
  6. Provisional share = provisional sums ÷ quoted before GST.
  7. Advance and retention = the percentage × the quoted amount with GST.

Assumptions

AssumptionDefaultNotes
GST rate18%Confirm the rate for your contract
ExclusionsBefore GSTEnter them on the same basis as the quote
Advance and retentionOn the amount with GSTMost payment terms are applied to the invoice value

The quality of the comparison depends on the exclusions estimate. If one contractor excludes the HVAC changes and another includes them, the comparison is only fair once you have put a realistic figure against the missing work.

Limitations

  • It compares price, not scope. Two quotes with the same total can describe very different offices. The only way to compare scope is line by line against the same drawings and specification.
  • It trusts your exclusions estimate. A low guess for a missing item flatters that quote.
  • It does not value programme or risk. A quote that finishes four weeks later may cost you four more weeks of rent on two premises.
  • It does not judge payment terms. It shows the cash involved; whether those terms are acceptable is a commercial decision.
  • It does not check arithmetic in the quotes. Check the quantities and totals on each quote separately.

Worked example

Suppose three quotes arrive for the same office. The figures below are invented for the example and are not market prices.

  • Quote A: 100 units, GST extra, nothing excluded.
  • Quote B: 110 units, GST included, nothing excluded.
  • Quote C: 88 units, GST extra, but the HVAC changes are excluded and you estimate them at 9 units.

At an 18% GST rate:

Quote AQuote BQuote C
Quoted before GST100.093.288.0
Items left out009.0
Comparable before GST100.093.297.0
Above the lowest7.3%Lowest4.1%

Quote B looked the most expensive on its headline figure but is the lowest once GST is treated the same way. Quote C looked cheapest but moves to second once its exclusion is added back. Quote A, which looked mid-range, is actually the highest.

How engineers use it

On a tender, a quantity surveyor or project manager prepares a tender comparison: every contractor prices the same bill of quantities against the same drawings, and the comparison is made line by line. Gaps are queried, unusual rates are explained, and exclusions are either priced in or removed before any recommendation is made.

This calculator is the summary at the top of that process. It is useful when quotes have arrived on different bases and you need a fair first view of where they stand before going into the detail.

When a professional design must replace it

Use the calculator to get quotes onto one basis and to decide which ones deserve a detailed review. Replace it with a line-by-line comparison against the same drawings, specification and quantities before you award the work, and have the contract terms (payment, retention, defects liability, delay damages and variations) reviewed before you sign.

Frequently asked

Because quotes are rarely priced on the same basis. One includes GST and another adds it; one includes the electrical work and another leaves it to you; one carries large provisional sums that may grow. The headline totals compare different scopes. Normalising them first shows what each will really cost you.

Anything you will need for the finished office that the quote does not cover: for example furniture, HVAC changes, fire alarm and sprinkler modifications, IT cabling, signage, landlord approval fees or the cost of work at night. Read the exclusions list on each quote and estimate what each missing item will cost you separately.

Allowances in a quote for work that cannot be priced exactly yet, such as a finish not yet chosen. The final cost replaces the allowance, up or down. A quote with a large share of provisional sums is less certain than its total suggests, so the calculator shows that share for each quote.

Not necessarily. The calculator compares price only. Programme, the contractor's track record, the specification behind each line and the payment terms all matter. A lower price on a thinner specification can cost more once variations start.

The calculator starts at 18%, but the rate that applies depends on the contract and the nature of the work. Confirm it with your accountant and change the field to match.