DG Set Sizing Calculator: A Preliminary kVA Rating for a Building
DG set sizing works out the kVA rating a diesel generator needs to carry a building's backup load. A screening calculation converts the running load to kVA, adds an expansion margin, keeps the set below its maximum continuous loading, checks the peak when the largest motor starts, and rounds up to the next common rating.
By Dhruv Agarwal · · 6 min read
DG set sizing calculator
Only the circuits the DG will feed: the essential load, not the whole building.
Share of the connected load running at the same time.
The biggest motor that may start while the rest of the load is running: a pump, compressor or lift.
Starting kVA as a multiple of the motor's running kVA. It depends on the starting method: direct-on-line (DOL) is highest, star-delta and soft starters lower, a VFD lowest. Check the figure with the DG supplier.
Assumptions (edit to match your project)
0.8 lagging is the usual planning figure. Use the measured or designed value if you have it.
Headroom so the set is not run flat out. 80% is a common planning figure; follow the supplier's rating for your duty.
Indicative DG rating
160 kVA
Next common rating in India at or above 157.5 kVA; about 128 kW at 0.8 PF. Confirm with the supplier.
Required capacity
157.5 kVA
Set by the running load with margin
Running load
105 kVA
84 kW at power factor 0.8
Loading at that rating
66%
79% with the expansion margin used; 89% while the motor starts
| Connected load | 120 kW |
| Running load at 70% diversity | 84 kW |
| Running load ÷ power factor 0.8 | 105 kVA |
| With 20% expansion margin | 126 kVA |
| ÷ 80% maximum loading | 157.5 kVA |
| Largest motor running (15 kW ÷ 0.8) | 18.8 kVA |
| Extra while it starts (× 3 − 1) | 37.5 kVA |
| Peak while the motor starts | 142.5 kVA |
| Required (larger of the two) | 157.5 kVA |
How this was calculated
- Running kW = 120 kW × 70% = 84 kW
- Running kVA = 84 / 0.8 = 105 kVA
- Sized on running load = 105 × (1 + 20%) / 80% = 157.5 kVA
- Motor running kVA = 15 / 0.8 = 18.75 kVA; extra starting kVA = 18.75 × (3 − 1) = 37.5 kVA
- Peak kVA = 105 + 37.5 = 142.5 kVA
- Required = max(157.5, 142.5) = 157.5 kVA → 160 kVA
- Loading = 105 / 160 = 66% today
Send this result on WhatsApp
Your figures go with the message, so our team can reply on them directly.
Send on WhatsAppIndicative figures for early planning, based only on the inputs and assumptions above. This is not a design, a quotation or a compliance check. A qualified engineer or consultant must confirm any figure before it is used to order, build or sign.
What it calculates
The calculator gives a preliminary kVA rating for a diesel generator (DG) set. It works out the running load in kW and kVA, the capacity needed once an expansion margin and a maximum continuous loading are allowed for, and the peak while the largest motor starts. It takes the larger of the two requirements and rounds it up to the next rating in a list of common DG ratings in India.
It also shows how heavily the recommended set would be loaded: today, with the expansion margin used up, and during the motor start. That tells you whether the set is likely to be oversized as well as whether it is big enough.
The result is for early planning: checking a landlord's backup provision, reserving plant space, or comparing options before an electrical engineer prepares the load schedule.
Inputs
Connected load on the DG is the total rating of everything the generator will feed, in kW. Enter only the essential load if the DG will not back up the whole building. Deciding what is essential comes first; sizing on the full connected load of a building usually produces a set that spends its life lightly loaded.
Demand (diversity) factor is the share of that connected load expected to run at the same time. Lights, air conditioning and pumps rarely all run at full output together.
Largest single motor is the biggest motor that may start while the rest of the load is already running: typically a transfer pump, an air compressor, a lift or a chiller compressor.
Motor starting multiplier is the motor's starting kVA as a multiple of its running kVA. It depends on the starting method. Direct-on-line (DOL) starting gives the highest surge, star-delta and soft starters less, and a variable frequency drive (VFD) the least. The default of 3 is a placeholder; confirm the figure with the DG supplier.
Future expansion margin is the growth you want to allow for.
The assumptions panel holds the load power factor and the maximum continuous loading of the set.
Method
- Running kW = connected load × diversity.
- Running kVA = running kW ÷ power factor.
- Sized on running load = running kVA × (1 + expansion margin) ÷ maximum loading.
- Motor running kVA = motor kW ÷ power factor.
- Extra starting kVA = motor running kVA × (starting multiplier − 1). The motor's running kVA is already inside the running load, so only the extra is added.
- Peak kVA = running kVA + extra starting kVA.
- Required kVA = the larger of steps 3 and 6.
- The recommended rating is the next value at or above the requirement in this list of common DG ratings in India: 15, 20, 25, 30, 40, 45, 62.5, 82.5, 100, 125, 160, 180, 200, 250, 320, 380, 400, 500, 625, 750, 1010, 1250, 1500 and 2000 kVA. Ranges differ between manufacturers, so confirm the available ratings with the supplier.
Loading is the running kVA divided by the chosen rating.
Assumptions
| Assumption | Default | Basis |
|---|---|---|
| Demand (diversity) factor | 70% | A planning figure for mixed office and light commercial loads |
| Load power factor | 0.8 | The power factor DG sets in India are normally rated at |
| Motor starting multiplier | 3 × running kVA | A placeholder; it depends on the starting method and the motor |
| Expansion margin | 20% | Room for growth in the essential load |
| Maximum continuous loading | 80% | Headroom below the set's rating for load steps and hot days |
Diversity is the assumption most worth questioning. A building with process loads that run around the clock, or a server room with its cooling, can have a demand factor close to 100%. An office with many small sockets can be well below 70%.
Limitations
- It is a single steady-state figure. It does not model the transient voltage and frequency dip when load is applied, which ISO 8528-5 deals with and which the supplier checks for the actual engine and alternator.
- It treats motor starting simply. Starting several motors together, motors on VFDs, and the order in which loads come back after a changeover all change the peak.
- It ignores harmonic loads. UPS systems, VFDs and LED drivers draw distorted current that can call for a larger alternator than the kVA alone suggests.
- It ignores site derating. High ambient temperature and altitude reduce what a set can deliver; the manufacturer's derating tables apply.
- It does not choose between standby and prime ratings. ISO 8528-1 defines different rating categories for different duties, and a set that runs for long hours every day is rated differently from one that only covers occasional outages.
Worked example
A 120 kW essential load at 70% diversity and 0.8 power factor, with a 15 kW pump as the largest motor, a starting multiplier of 3, a 20% expansion margin and an 80% maximum loading:
| Step | Calculation | Result |
|---|---|---|
| Running load | 120 kW × 70% | 84 kW |
| Running load in kVA | 84 ÷ 0.8 | 105 kVA |
| With expansion margin | 105 × 1.2 | 126 kVA |
| Sized on running load | 126 ÷ 80% | 157.5 kVA |
| Motor running kVA | 15 ÷ 0.8 | 18.75 kVA |
| Extra while it starts | 18.75 × (3 − 1) | 37.5 kVA |
| Peak during the start | 105 + 37.5 | 142.5 kVA |
| Required | larger of 157.5 and 142.5 | 157.5 kVA |
The next common rating at or above 157.5 kVA is 160 kVA, about 128 kW at 0.8 power factor. At that rating the set runs at 66% today, 79% once the expansion margin is used up, and 89% while the pump starts. Here the running load, not the motor, sets the size.
Change the largest motor to 30 kW with the same multiplier and the picture changes. Its running kVA becomes 37.5, the extra while starting 75 kVA, and the peak 180 kVA. The motor start now governs, and the recommended rating moves up to 180 kVA. A soft starter on that motor could bring the multiplier down and the rating back.
How engineers use it
An electrical engineer starts from a load schedule rather than a single connected-load figure: every circuit on the essential board, its rating, its power factor and how it is used. Diversity is applied load by load. Motors are listed with their starting method, and the start sequence after a mains failure is planned so that large motors do not start together.
The DG supplier then checks the shortlisted set against that schedule: the alternator's voltage dip on the largest motor start, the engine's response to the first block of load, derating for the site, and the rating category for the duty. Noise and emission requirements under CPCB norms apply to the set and commonly drive the acoustic enclosure and the exhaust design, so they are checked for the specific site.
A screening number like this one is still useful at the start. It shows whether a landlord's existing set is in the right range, how much plant space to reserve, and which assumption (usually diversity or the largest motor) the rating is most sensitive to.
When a professional design must replace it
Use the calculator to compare options and to start the conversation with a supplier. Replace it with a load schedule and sizing by a qualified electrical engineer before a set is ordered, before the changeover and distribution design is fixed, and whenever the load includes large motors, lifts, UPS systems, VFDs or process equipment. The engineer and the supplier confirm the rating, the paralleling arrangement if any, and the installation requirements of NBC 2016 Part 8 and the applicable electrical safety regulations.
Standards referenced
- ISO 8528-1 — Generating sets: application, ratings and performance (ISO)
- ISO 8528-5 — Generating sets: performance, including response to load changes (ISO)
- NBC 2016, Part 8, Section 2 — Electrical and allied installations (Bureau of Indian Standards)
- CPCB norms — Emission and noise limits for diesel generator sets (Central Pollution Control Board)
Frequently asked
Related
- Power Backup: Sizing DG and UPS Around an Essential Load
- DG Set vs UPS: What Each One Is Actually For
- UPS Battery Runtime Calculator: Backup Time from Load and Batteries
- Sanctioned Load: The Power a Building Is Allowed to Draw
- Power Factor Correction: Why the Electricity Bill Cares About It
- Office Electrical Load Planning
More in Calculators
- Duct Size Calculator: Round and Rectangular Ducts by the Velocity Method
- Facade Glazing Calculator: Vision Glass, Spandrel and WWR
- Meeting Room Size Calculator: Room Dimensions from the Table
- Office Seat Capacity Calculator: How Many People Fit in a Floor?