Data Centres and Server Facilities: Power, Cooling and Redundancy
Data centre construction is building around power and heat. The electrical and cooling plant, and how much of it is duplicated, decide the layout, structure and cost far more than the IT hall does. For enterprise and edge facilities, the redundancy level, floor loading, cooling approach and phasing should be fixed before the architecture is drawn.
By Dhruv Agarwal · · 4 min read
Power and cooling are the building
A data centre looks like a room full of racks. Commercially it is a power and cooling plant with an IT hall attached. Electrical rooms, UPS and battery rooms, generators, cooling plant and the routes between them take most of the area and most of the budget, and they decide the structure and the site layout.
The misconception worth correcting is that a data centre is a large server room fitted out the same way. A server room borrows the building's resilience; a data centre has to provide its own. Choosing too little duplication exposes the business to outages, and choosing too much locks up capital in plant that may never be needed. This page covers enterprise and edge facilities, from a dedicated floor to a small standalone building; very large campuses are a different scale of project.
Spaces and the services behind them
| Space | What it must do | Service |
|---|---|---|
| IT hall (white space) | Hold racks with continuous cooling, power and cabling | Server room and data centre MEP |
| UPS, battery and generator areas | Keep the load running through a supply failure | Power backup: DG and UPS |
| Electrical rooms and incoming supply | Distribute power along the chosen redundant paths | Electrical works HT/LT |
| Cooling plant | Remove the heat the IT load produces, day and night | HVAC systems design |
| Detection and suppression | Early warning, suppression suited to electronics | Fire detection and alarm |
| Cabling | Structured cabling with room for growth | Networking and structured cabling |
| Monitoring | Alarms that reach someone who can act | Building management systems |
N, N+1 and 2N: what redundancy buys
"N" is the capacity the load needs. Redundancy describes how much is provided beyond it.
| Level | What it means | What it protects against |
|---|---|---|
| N | Exactly enough capacity | Nothing: a failure or maintenance reduces capacity |
| N+1 | One spare unit beyond need | One unit failing or being serviced |
| 2N | Two complete independent systems | Loss or maintenance of an entire system |
Redundancy also applies to distribution paths, not only to equipment. Two UPS units feeding a single switchboard still share one point of failure. ANSI/TIA-942 sets out rating levels for data centre infrastructure, and ISO/IEC 22237-1 and EN 50600-1 define a classification by availability, from a single path up to fault-tolerant multi-path designs. Which level is right depends on what an outage costs the business, which is a decision for the owner, informed by the MEP consultant.
Raised floor or overhead, and containment
A raised access floor gives an underfloor air path and cable space. Overhead cabling with cooling delivered by in-row or perimeter units is the other common approach, and a solid floor carries heavy racks more easily. The decision follows the cooling design.
Containment, enclosing the hot or cold aisle, stops supply and return air mixing so the cooling does useful work. It also changes how fire detection and suppression reach the racks, so the fire consultant has to design with the containment, not around it.
Structure is the item most often assumed. Dense racks, battery rooms and plant are far heavier than office loads; the current revision of TIA-942 addresses floor loading capacity for this reason. The project's structural engineer must confirm the slab against the real layout.
Fire, phasing and the smaller room
Fire protection combines early-warning detection with suppression chosen not to damage the equipment it protects. Gas-based systems need a sealed room to work, which affects walls, ceilings, doors and every penetration. What a facility requires is decided under NBC 2016, Part 4 by the fire consultant and the authority having jurisdiction.
Phasing is where many facilities save capital: build the shell and main routes for the final capacity, then add power and cooling modules as the load arrives, with tie-in points provided from day one. For a single equipment room inside an office, start with what to settle first for a server room in an office.
Common mistakes
- Choosing redundancy by habit. The level should follow the cost of an outage.
- Duplicating equipment but not paths. A shared switchboard defeats two UPS units.
- Assuming the slab is fine. Battery rooms concentrate load and need checking.
- Backing up servers but not cooling. The outage is delayed, not avoided.
- No space for phase two. Later modules end up squeezed into live areas.
What to ask before design starts
- What does an hour of outage cost, and what redundancy does that justify?
- Is redundancy applied to distribution paths as well as equipment?
- Raised floor or overhead, and why, given the cooling design?
- Has the structural engineer checked the slab against racks, batteries and plant?
- How is the first phase set up for the later ones?
Standards referenced
Data centre infrastructure in ANSI/TIA-942; general concepts and availability classification in ISO/IEC 22237-1 and EN 50600-1; fire and life safety in NBC 2016, Part 4. Redundancy, loads, cooling and fire requirements for a specific facility are established by the project's MEP, structural and fire consultants and the authority having jurisdiction.
Standards referenced
- TIA-942 — Telecommunications infrastructure standard for data centers (ANSI/TIA-942-C) (Telecommunications Industry Association)
- ISO/IEC 22237-1 — Data centre facilities and infrastructures - Part 1: General concepts (ISO)
- EN 50600-1 — Data centre facilities and infrastructures - Part 1: General concepts (CEN-CENELEC)
- NBC 2016, Part 4 — Fire and life safety (Bureau of Indian Standards)
Frequently asked
Related
- Server Room and Data Centre MEP: Cooling, Power and Resilience
- Office Server Room Design
- Raised Access Floor: The Void That Runs the Office
- Power Backup: Sizing DG and UPS Around an Essential Load
- DG Set vs UPS: What Each One Is Actually For
- Raised Access Floor vs Surface Trunking: Routing Power and Data