PIR Insulation Panel — Lambda, Thickness and Fire
A PIR insulation panel is a self-supporting sandwich panel with a rigid closed-cell polyisocyanurate foam core bonded between two metal skins, used for roofs and walls. It gives among the best thermal performance per millimetre of the common industrial insulations, but the core is combustible, so its EN 13501-1 fire class must be named.
By Dhruv Agarwal · · 1 min read
What it is
A rigid polyisocyanurate foam core bonded between two metal skins, supplied as a self-supporting sandwich panel for roofs and walls. The foam is closed-cell, which is why it insulates so well for its thickness.
Specification at a glance
| Property | Typical specification |
|---|---|
| Core | Polyisocyanurate, closed cell |
| Thermal conductivity | Approximately 0.022 W/mK |
| Core density | 38 — 45 kg/m³ typical |
| Panel thickness | 30mm — 150mm |
| Skins | Pre-painted Galvalume, 0.45mm — 0.60mm |
| Standard | EN 14509 for the panel system |
| Fire class | Named EN 13501-1 class; core is combustible |
Thickness against U-value
Indicative, before thermal bridging at fixings and joints:
| Core thickness | Approximate U-value |
|---|---|
| 40mm | ~0.52 W/m²K |
| 50mm | ~0.42 W/m²K |
| 80mm | ~0.27 W/m²K |
| 100mm | ~0.21 W/m²K |
| 150mm | ~0.14 W/m²K |
The ECBC 2017 target for the climate zone sets which row applies. On a single-storey industrial building the roof usually governs, because it takes the highest solar incidence of any surface.
Why it gets specified
Best thermal performance per millimetre of the common industrial insulations, so it wins wherever build-up depth is constrained or the U-value target is demanding.
Single-fix envelope. The panel is structure, insulation, weather line and finish in one operation, which compresses the programme against a built-up system.
Where projects go wrong
- Thickness chosen by habit rather than from the ECBC target for the climate zone.
- Fire class unstated. "PIR" is not a fire specification.
- Combustible core behind a combustible outer panel in a ventilated cavity — the assembly behind the worst facade fires.
- Joints and fixings ignored in the U-value. The installed assembly underperforms the datasheet, sometimes substantially.
- Panels stacked and handled carelessly. A crushed edge cannot be made weathertight afterwards.
Standards referenced
Opaque assembly U-value targets under ECBC 2017. Panel system requirements under EN 14509. Reaction-to-fire classification to EN 13501-1.
Standards referenced
- ECBC 2017 — Building envelope — opaque assembly U-value (Bureau of Energy Efficiency)
- EN 13501-1 — Reaction to fire classification (CEN-CENELEC)
- EN 14509 — Self-supporting double skin metal faced insulating panels (CEN-CENELEC)
Frequently asked
Related
More in Materials
- Polyamide Thermal Break Strip in Aluminium Profiles
- Polycarbonate Skylight Sheet for Industrial Roofs
- Porcelain Tile Cladding for Ventilated Facades
- Pre-Insulated Duct — PIR Panel Ductwork