PEB Industrial Buildings & Warehouses
By Dhruv Agarwal · · 2 min read
What we deliver
Pre-engineered factories, warehouses, logistics sheds and industrial buildings — structure, cladding, civil foundations and flooring, and MEP delivered together rather than split between a steel supplier and several site contractors.
An industrial building is judged on a few things: clear span, clear height, floor capacity, and how soon it can start operating. PEB is chosen because it wins on all four — provided the foundations, the steel and the services are ready for each other.
Scope of works
| Stage | What we deliver |
|---|---|
| Design | Frame, bracing and secondary members to IS 800 and IS 875 |
| Civil | Foundations, plinth, anchor bolts, grade slab |
| Fabrication | Primary and secondary steel, shop-primed |
| Erection | Frames, bracing, purlins and girts |
| Envelope | Roof and wall sheeting, insulated panels where specified |
| Openings | Rolling shutters, dock doors, ventilators, skylights |
| Services | Electrical, lighting, firefighting and plumbing |
| Handover | Inspection, documentation |
What drives the cost
Clear span and eave height · crane capacity · roof and wall cladding specification · insulation · floor loading and slab thickness · number of dock openings · fire protection required for the stored goods · site access for steel delivery and cranes.
Where projects go wrong
- Steel arrives before foundations are ready. Erection stalls and the steel sits in the open.
- Grade slab designed without racking loads. High-bay racking concentrates large point loads on the floor.
- Fire requirements set after the design. Sprinklers and hydrants change the roof height, water storage and pump room.
- Ventilation and daylighting ignored. Large sheds without them are hot and dark and need lighting all day.
- Drainage undersized. A large roof collects a great deal of water in a monsoon downpour.
Why Hagerstone
Single-partner execution — PEB, civil, MEP and interiors under one integrated team, so foundations, steel and services are sequenced by one programme.
15 welders, 15 fitters, a 35-member firefighting team and a 53-member site team in-house, under ISO 9001 / 14001 / 45001 and 79+ quality checkpoints.
Standards referenced
Steel design to IS 800:2007. Wind loading to IS 875 (Part 3). Fire and life safety for industrial and storage occupancy under NBC 2016, Part 4.
Standards referenced
- IS 800:2007 — General construction in steel — code of practice
- IS 875 (Part 3) — Wind loads on buildings
- NBC 2016, Part 4 — Fire and life safety — industrial and storage occupancy