Construction Tolerances: Why Nothing Is Built Exactly to Drawing
A construction tolerance is the permitted difference between the size or position shown on a drawing and what is actually built. Every trade works to its own tolerance: in-situ concrete is less precise than factory-made steel, aluminium or glass. Where trades meet, the design must provide enough adjustment to absorb the difference.
By Dhruv Agarwal · · 2 min read
Why it matters on a project
Many disputes on site start with "it doesn't fit". A facade bracket cannot reach the slab edge, a partition head meets a beam lower than drawn, or a raised floor cannot be levelled on an uneven slab. Most of these trace back to tolerances that were never compared between trades.
Different trades, different accuracy
| Trade | Made where | Relative accuracy |
|---|---|---|
| In-situ concrete frame | On site | Lowest |
| Structural steel | Factory, erected on site | Medium |
| Masonry and blockwork | On site | Low to medium |
| Aluminium and glass facade | Factory | High |
| Joinery and fit-out elements | Factory or workshop | High |
The actual values for a project come from its specification and the codes it references; concrete tolerances are addressed in IS 456, and the principles of expressing and managing accuracy are set out in ISO 1803 and BS 5606.
How good projects manage it
- One control grid and benchmark set shared by every trade, set out to ISO 4463-1 principles.
- Interface details that state adjustment, such as slotted bracket holes, packers and shims, sized for the combined deviation.
- A survey of the as-built structure before fabrication of facade or joinery starts.
- Hold points where the next trade checks and accepts the surface it builds on.
- As-built records so later trades work from real dimensions.
Common mistakes
- Designing a factory-made element to drawing dimensions with no allowance for the structure it fixes to.
- Fabricating before surveying the structure.
- Each trade setting out from its own reference.
- Using up adjustment in the first installation step, leaving none for the next.
- Treating out-of-tolerance work as a site problem instead of raising it at the hold point.
Standards referenced
Principles of accuracy in ISO 1803 and BS 5606; setting out under ISO 4463-1; concrete tolerances in IS 456. Tolerance values and interface adjustments for a specific project must be set out in its specification by the design team.
Standards referenced
- ISO 1803 — Building construction — tolerances — expression of dimensional accuracy — principles and terminology (ISO)
- ISO 4463-1 — Measurement methods for building — setting-out and measurement (ISO)
- BS 5606 — Guide to accuracy in building (British Standards Institution)
- IS 456 — Plain and reinforced concrete — code of practice (Bureau of Indian Standards)
Frequently asked
Related
- Curtain Wall Brackets: How a Facade Hangs on the Building
- As-Built Drawings: The Record of What Was Actually Installed
- Movement Joint: Where a Building Is Allowed to Move
- Mullion and Transom: The Grid That Carries a Curtain Wall
- Raised Access Floor: The Void That Runs the Office
- Snagging: The Inspection That Decides How Handover Feels
More in Glossary
- Harmonic Distortion: The Hidden Load in a Modern Office
- Interstitial Condensation: Moisture Inside the Wall or Roof
- Power Factor Correction: Why the Electricity Bill Cares About It
- Silicone Weatherseal: The Joint That Keeps the Facade Dry