Pantry and Cafeteria Fit-Out: Services Decide the Position
Pantries and cafeterias are positioned by services, not by layout preference. They need drainage with continuous fall to an existing stack, extract to outside, water supply, and concentrated power — and of those, drainage is usually the constraint that fixes the location before any other consideration.
By Dhruv Agarwal · · 2 min read
Find the stacks before drawing the plan
The usual process is backwards: the layout is designed, a pantry is placed where it suits the plan, and the services team is then asked to serve it.
The order that works is to establish where existing soil and waste stacks are, where extract can be routed, and where water and power can reasonably reach — and to place wet areas accordingly. Everything else on a floor is more flexible than drainage.
The four services, in order of constraint
| Service | Why it constrains | Flexibility |
|---|---|---|
| Drainage | Gravity; needs fall to an existing stack | Very low |
| Extract | Must route through the building and discharge | Low |
| Water supply | Pressurised, routes reasonably freely | Moderate |
| Power | Concentrated load; needs a dedicated circuit | Moderate |
Drainage is almost always the binding constraint. Floor build-up available for a fall is limited, and a long run either runs out of fall or needs pumping — which introduces equipment, noise, maintenance and something that can fail while nobody is watching.
Plumbing provisions sit in NBC 2016, Part 9, with ventilation in NBC 2016, Part 8 and ventilation rates commonly referenced to ASHRAE 62.1.
Name what you are actually building
| Tea point | Pantry | Cafeteria with cooking | |
|---|---|---|---|
| Water and sink drainage | Yes | Yes | Yes, plus floor drainage |
| Refrigeration | Sometimes | Yes | Yes, larger |
| Extract | Minimal | Moderate | Substantial, with grease management |
| Power | Modest | Concentrated | Heavy, or gas |
| Back of house | None | Small | Preparation, storage, wash-up, waste |
| Fire considerations | Standard | Standard | Suppression and dampers likely |
Briefs frequently say "pantry" and mean "cafeteria". The services difference is large, and it is better established at brief stage than during coordination.
What consumes the area
A cafeteria brief given as a seat count understates the space required. Also needed:
- Servery and queuing space, which backs up at peak
- Circulation between tables that people can actually pass through
- Back-of-house preparation and storage
- Wash-up and equipment space
- Waste storage and its removal route
- Sometimes a separate route for deliveries
And the sizing driver is peak usage, not headcount — a single lunch sitting needs far more seats than a staggered one, so the operating pattern belongs in the brief.
Construction details that matter
- Impervious, slip-resistant flooring, with coved junctions at walls in wet areas
- Falls to drainage designed into the screed wherever the floor is washed
- Waterproofing beneath wet areas, properly detailed at upstands
- Ventilation sized for the space's actual use, not the general office rate
- Acoustic treatment — hard, cleanable surfaces make these rooms loud, and a noisy cafeteria empties quickly
- Access to isolation valves, traps and equipment for maintenance
Standards referenced
Plumbing provisions, including water supply and drainage, in NBC 2016, Part 9; ventilation provisions in NBC 2016, Part 8; ventilation rates commonly referenced to ASHRAE 62.1; fire and life safety provisions in NBC 2016, Part 4. Drainage design, extract routing, ventilation rates and any fire requirements for a specific facility must be established by the project's consultants and the authority having jurisdiction.
Standards referenced
- NBC 2016, Part 9 — Plumbing services — water supply and drainage (Bureau of Indian Standards)
- NBC 2016, Part 8 — Building services — ventilation (Bureau of Indian Standards)
- NBC 2016, Part 4 — Fire and life safety (Bureau of Indian Standards)
- ASHRAE 62.1 — Ventilation for acceptable indoor air quality (ASHRAE)
Frequently asked
Related
- Office Pantry and Washroom Plumbing
- CPVC vs GI Pipe for Building Plumbing: Corrosion, Joints and Service Life
- Epoxy vs Vinyl for Industrial Floors: Chemicals, Traffic and Downtime
- MEP Coordination for Interiors: Where Fit-Out Programmes Lose Time
- Vitrified Tile — Full Body, GVT and Double Charge
- Factory Canteen and Amenity Block Planning: What Sets the Size
More in Interior Fit-Out
- Reception and Front of House: The Space That Sets Expectations
- False Ceilings & Partitions
- Fit-Out MEP Coordination
- Office Flooring — Carpet Tile, Vinyl, Stone and Raised Access