FRLS and LSZH Cable — Fire Performance in Cables
FRLS (Flame Retardant Low Smoke) cable resists flame spread and produces less smoke and acid gas while burning; LSZH cable does the same with zero halogen content. Neither keeps a circuit working in a fire - that is fire-survival cable, a separate product for circuits that must keep operating.
By Dhruv Agarwal · · 1 min read
What it is
A family of cable specifications defined by how the cable behaves in a fire, rather than by its electrical properties.
Three distinct things get confused in Indian specifications:
| Type | What it does |
|---|---|
| FRLS | Resists flame spread, reduces smoke and acid gas while burning |
| LSZH | As above, with zero halogen content |
| Fire survival | Keeps the circuit energised during a fire for a stated period |
FRLS is not fire resistant. It burns; it just burns less badly.
Why smoke is the specification that saves lives
Most fire deaths are from smoke inhalation, not burns. A standard PVC cable in a burning shaft produces dense black smoke and hydrogen chloride gas, which both obscures escape routes and attacks the lungs. In a stair core or a basement, that is the mechanism that kills.
Reducing smoke and acid gas from the very cables that run through escape routes is therefore a life safety measure, not a specification upgrade.
Mapping cable type to location
| Location or duty | Typical requirement |
|---|---|
| General distribution in open areas | FRLS |
| Escape routes, stairs, lobbies | LSZH preferred |
| Basements and enclosed shafts | LSZH |
| Fire pumps, pressurisation fans | Fire survival |
| Fire alarm and emergency lighting | Fire survival |
| Data centres and critical rooms | LSZH |
Where projects go wrong
- FRLS specified for fire pumps. The pump stops when the cable burns through — exactly when it is needed.
- One grade across the whole project, either overspending everywhere or underspecifying in the places that matter.
- Fire-survival cable installed with ordinary accessories. The rating belongs to the complete system, including glands, clips and supports; plastic clips melt and drop the cable.
- Certificates not verified against the delivered drum.
Standards referenced
Fire and life safety provisions for services under NBC 2016, Part 4. Cable construction under IS 7098. Fire performance test methods under IEC 60332.
Standards referenced
- NBC 2016, Part 4 — Fire and life safety — services (Bureau of Indian Standards)
- IS 7098 — Cross-linked polyethylene insulated cables (Bureau of Indian Standards)
- IEC 60332 — Tests on electric cables under fire conditions (IEC)
Frequently asked
Related
More in Materials
- FRP Translucent Sheet for Roof Lights and Cladding
- Galvalume Sheet — Coating, Grades and Service Life
- GI Duct — Gauge, Construction and Leakage Class
- GI Pipe — Classes, Threading and Where It Still Belongs