Commissioning: Proving the Building Actually Works
Commissioning is the process of proving that installed systems work as designed — individually and together — and recording the evidence. It goes beyond testing that equipment switches on: it covers balancing, control response, interfaces between systems and performance against the design intent.
By Dhruv Agarwal · · 2 min read
Why it matters on a project
Most post-occupancy complaints about a new office are not construction defects. They are commissioning gaps.
"Half the floor is cold and the other half is warm." "The meeting room is stuffy." "The lights do not respond to the sensors." In almost every case the equipment is correct, installed and working — it has simply never been set up to deliver what the design intended.
That is why commissioning deserves attention from the client side, even though it is the least visible part of a fit-out.
Three different activities that get confused
| Activity | Question it answers | Visible? |
|---|---|---|
| Testing | Does this equipment work? | Partly |
| Commissioning | Does the system deliver the design intent? | No |
| Snagging | Does the finish look right? | Entirely |
A project can pass the first and third and fail the second completely, and nothing on a walk-through would reveal it.
The parts most often missed
- Air balancing. Rooms get the airflow the design allocated, measured and recorded. Without it, distribution is decided by pipe and duct resistance rather than by design.
- Control strategy. Not whether controls function, but whether they behave as intended — setpoints, schedules, sensor response, sequencing.
- Interfaces between systems. Fire alarm to air handling, dampers, access control, generator changeover. These belong to no single contractor and are skipped unless scheduled and witnessed.
- Fresh air quantities. Frequently assumed rather than measured, with ventilation rates commonly referenced to ASHRAE 62.1.
- Electrical testing records, in line with the installation practice adopted, commonly with reference to IS 732.
Testing and commissioning provisions for building services sit within NBC 2016, Part 8, and the specific regime for a project must be set by the MEP consultant.
What to insist on
Ask for numbers, not statements. A commissioning record should show measured values against design values, room by room and system by system, with the date and who took them.
Ask for the cause-and-effect test record for interfaces, witnessed.
And put commissioning in the programme as a duration with a start date, not as an activity that happens in whatever time remains.
Common mistakes
- Compressing it when the programme slips. The consequences surface after occupation, when they are hardest to attribute.
- Accepting a signature instead of readings. No data means no commissioning.
- Assuming interfaces were tested. They belong to nobody by default.
- Occupying before commissioning completes. Balancing a floor full of people and furniture is far harder than balancing an empty one.
- Treating snag-free as proof. Appearance and performance are unrelated here.
Standards referenced
Testing and commissioning provisions for building services in NBC 2016, Part 8; ventilation rates commonly referenced to ASHRAE 62.1; electrical installation practice in IS 732. The commissioning scope, method and acceptance criteria for a specific project must be established by the project's MEP consultant.
Standards referenced
- NBC 2016, Part 8 — Building services — testing and commissioning
- ASHRAE 62.1 — Ventilation for acceptable indoor air quality
- IS 732 — Code of practice for electrical wiring installations